hitex inspection and audit trail

Hitex follow a rigorous audit process to ensure compliance is met on every completed project.

The six step process is;

1.     Timber Frame Inspection.  

The Hitex foreman or Hitex Registered Applicator will inspect the project 10-14 days out from the cladding commencement to check and discuss various items with the builder. 

For example

bullet

OSH Safety in place

bullet

Nogging/Internal corners and soffit

bullet

Stop ends – leave lead, butynol 100mm past

bullet

Scaffolding layout and timing

bullet

Mid floor timber alignment

bullet

Protruding beams and mounting plates

bullet

Window flashings organised

bullet

Windows arrive when

bullet

Timber straightness (visual)

bullet

etc

This ensures the builder and applicator are working in sync for the benefit of the project.

2.     Ready to Start Inspection

The foreman or applicator will return to site 3 days before cladding commencement to conduct a final check to ensure all is ready.

This may entail checking:-

bullet

Slab and bottom plate alignment

bullet

Ground lines confirmed

bullet

Roof flashings installed

bullet

Stop ends installed

bullet

Scaffolding OK and complete

bullet

Mid floor moisture content

bullet

Window flashings on site

bullet

Windows installed

bullet

Soffits installed

bullet

etc

The Hitex sheets can now be fixed with confidence.

3.      Fixing Release Certificate

Once the fixing of the Hitex sheets is complete, the signing off process is done involving the fixer (to indicate the fixing has been installed correctly) and the plasterer (indicating they are happy to accept the fixing).  The plastering can now commence.

4.      Final Release Certificate

On completion of the plastering, a final release is done confirming the work has been completed in accordance with the contract, all items have been left clean, waste is ready for removal and the work can now be handed over to the client.

5.      Hitex Works Compliance Record.

At the time of Final Release, a Works Compliance Record is completed confirming:

bullet

the type of Hitex system used

bullet

compliance with Hitex Trade Practice, eg:

bullet

compliance with certain segments of NZ Building Code

This document can be forwarded to council as confirmation of compliance and placed on LIM Report.

6.      Warranty of Fitness

At this point the Hitex Audit Manager visits the site and reconfirms that the works have complied with Hitex Trade Practice requirements at the time of inspection.

The items checked include

bullet

materials supplied

bullet

stop ends to decks/roofs installed

bullet

window flashings installed

bullet

protrusions and penetrations sealed

bullet

parapet tops installed with correct specifications

If all of the above is correct and complete then the Hitex Warranty and Hitex Maintenance Manual may be issued.

 

Back to the top

Page last updated Tuesday, 08 March 2005

HiTex Building Systems Ltd
PO Box 258056, Greenmount, Auckland, New Zealand, Tel +649 274 0246, Fax +649 274 0937,
Email
info@hitex.co.nz

Site designed and maintained by Webford Design